KARACHI: The National Highway Authority (NHA) has shortlisted three bidders for the construction of Section-III of the Hyderabad-Sukkur Motorway (M-6), advancing the procurement process for a key part of Pakistan’s north-south motorway network.
According to The Express Tribune, the technically qualified bidders will now proceed to the financial evaluation stage, where their proposals will be opened for the 64.61-kilometre stretch between Nawabshah and Naushahro Feroze.
The NHA reviewed eight technical bids for the construction package, disqualifying four construction companies and joint ventures over non-compliance with documentation requirements.
Procurement Process
The tender for Section-III was advertised on August 25, 2026, while bids were opened during the first week of September.
The procurement is being conducted through a single-stage, two-envelope international open competitive bidding process, following the OPEC Fund’s procurement principles and procedures.
Pakistan to Invite Bids for FESCO, GEPCO and IESCO Privatisation in Q1 2027
Part of Major Motorway Network
The Nawabshah-Naushahro Feroze section is part of the planned six-lane Hyderabad-Sukkur Motorway, which aims to improve road connectivity between Sindh and Punjab.
The wider M-6 project is intended to complete Pakistan’s north-south motorway network, linking Karachi with Peshawar. However, the project has experienced repeated delays spanning more than five years.
You may also like
-
Pakistan to Invite Bids for FESCO, GEPCO and IESCO Privatisation in Q1 2027
-
Pakistan Plans 20% Windfall Tax on Oil Refineries to Raise Rs25 Billion
-
Australia Sanctions Two Men Over Iran-Linked Antisemitic Attacks
-
Oil Prices Rise as Middle East Attacks Raise Supply Concerns
-
Fatima Fertilizer Rewards Farmers in First Sarsabz Nitrophos Incentive Scheme Ceremony