National Accountability Bureau inquiry into alleged irregularities in Pakistan’s power transmission projects

NAB has launched inquiries into alleged irregularities involving two major power transmission projects.

NAB Opens Inquiry into Alleged Irregularities in Two Power Transmission Projects

The accountability watchdog has sought explanations and inquiry reports from the Power Division over alleged procurement violations and a disputed Rs1.282 billion tax payment

ISLAMABAD: The National Accountability Bureau (NAB) has initiated an inquiry into alleged irregularities in two major power transmission projects involving the Ministry of Energy’s Power Division, National Grid Company (NGC) and other officials, Business Recorder reported.

NAB has sought a detailed response from the Power Division and its attached entities regarding concerns raised by the Senate Standing Committee on Economic Affairs about the 765kV Dasu-Islamabad Transmission Line Project (Lot-IV) and ADB-40 IB-2022 Lot II-A, involving ACSR Bunting Conductor.

The inquiry follows a reference by the Senate committee under the National Accountability Ordinance, 1999.

In a letter, NAB Additional Director Sajid Ali, writing on behalf of the Director General, asked the Power Division to explain its position on the allegations and provide attested copies of all inquiry and fact-finding reports related to the projects.

Senate committee flags Rs1.282 billion payment

The development follows objections raised by the Senate committee, headed by Senator Saif Ullah Abro, over an alleged irregular payment of Rs1.282 billion in taxes to a contractor associated with the 765kV Islamabad West Grid Station project.

During earlier proceedings, the committee questioned the Power Division’s explanation and expressed concern over discrepancies in briefings provided by officials of the National Transmission and Despatch Company (NTDC) and NGC.

The committee was also informed that an audit objection had been raised during certification of the foreign-funded project. The matter was discussed at Departmental Accounts Committee (DAC) meetings, with further consideration expected by the Public Accounts Committee (PAC).

Auditor General officials disputed aspects of the Power Division’s earlier account, saying the audit had identified a material deviation and that the department’s position had not resolved the concerns.

Senator Abro maintained that the contract documents stated quoted rates included all taxes. He also highlighted an approximately Rs9 billion difference between the lowest and second-lowest bids.

Pakistan, Saudi Arabia and Türkiye Reaffirm Collective Defence Commitment

The chairman directed that the allegedly irregular Rs1.282 billion payment be recovered from the contractor, warning that the matter could otherwise be referred to FIA and NAB.

NAB also examines bunting conductor case

The Senate committee separately raised concerns over alleged involvement of NESPAK officials in the ADB-40 IB-2022 Lot II-A project concerning ACSR Bunting Conductor.

It directed the Power Division to submit a detailed report on action taken against the officials concerned and asked the Economic Affairs Division to ensure the Secretary Power Division attended the next meeting.

The committee had also called for the bunting conductor case to be referred to FIA and NAB.

NAB has now initiated inquiries into both matters, focusing on allegations of procurement-rule violations and seeking relevant records to proceed with the investigations.