K-IV water supply project infrastructure designed to transport water from Keenjhar Lake to Karachi.

WAPDA briefs National Assembly members on progress and revised completion timeline for Karachi’s K-IV water project.

K-IV Water Project Karachi’s Major Supply Scheme Expected to Be Completed by June 2027

WAPDA briefs a National Assembly sub-committee on project delays, revised plans and the first phase designed to supply 260 million gallons of water daily.

The K-IV water project is now expected to be completed by June 2027, according to WAPDA officials. They shared the revised timeline during a meeting of a National Assembly sub-committee on Tuesday.

The sub-committee of the National Assembly Standing Committee on Water Resources reviewed progress on the Greater Karachi Bulk Water Supply Scheme. It also examined delays, design problems, planning and accountability.

Chairman Muhammad Idrees led the meeting. Members stressed that the project is essential to meeting Karachi’s growing water needs. They also called for timely completion, noting that both the federal and Sindh governments consider it a priority.

K-IV Project Faces Revised Completion Timeline

During the briefing, WAPDA officials traced the project’s history and explained the reasons behind its delays.

The Sindh government conceived the K-IV project in 2003. Its main objective was to address Karachi’s rising demand for potable water and reduce the city’s supply shortfall.

Consultants conducted the feasibility study in 2006-07. Later, the Executive Committee of the National Economic Council (ECNEC) approved the original Phase-I PC-I on July 18, 2014.

The detailed design was completed in 2015. The government then awarded the execution contract to the Frontier Works Organisation (FWO). Construction began in July 2016, with December 2018 set as the original completion deadline.

Pakistan-China Energy Cooperation Both Countries Move to Fast-Track LPG and MoGas Projects

However, design-related issues emerged during construction. Work continued until 2018, when concerns over the project’s design came to light.

A third-party investigation commissioned by the Sindh government subsequently identified shortcomings in the design.

WAPDA Takes Over Project Implementation

The federal government took up the project in 2020 under the Karachi Transformation Plan. The Ministry of Water Resources also became involved.

WAPDA formally took over the project in April 2021. It began mobilisation in September 2022.

Initially, officials expected completion by October 2023. However, delays and revised planning pushed the projected deadline to June 2027.

WAPDA informed the committee that it had shared the revised design and planning with the Planning Commission and the federal government.

K-IV Scheme Designed to Supply 650 MGD

The original K-IV plan envisages supplying 650 million gallons per day (MGD) from Keenjhar Lake in Thatta district to Karachi.

The scheme consists of three phases:

  • Phase-I: 260 MGD
  • Phase-II: 260 MGD
  • Phase-III: 130 MGD

The first phase is currently being executed by WAPDA under the Ministry of Water Resources. It aims to deliver 260 MGD to Karachi through three termination points: Pipri, North East Karachi (NEK) and Manghopir.

The project includes an intake structure at Keenjhar Lake and a gravity channel. It also features pumping facilities, a pressurised pipeline, three reservoirs and filtration plants.

Sindh Government to Manage Distribution System

The Sindh government is responsible for the distribution and augmentation system. Its responsibilities also include power supply arrangements, land acquisition and right-of-way clearance.

Meanwhile, the Karachi Water and Sewerage Corporation (KW&SC), Government of Sindh, will operate and maintain the scheme.

WAPDA officials told the committee that Karachi’s water requirement stands at around 1,200 MGD. Therefore, completing K-IV remains critical to improving bulk water supplies to the city.

The sub-committee also sought details about progress and responsibility for the delays. Members emphasised that further delays would worsen pressure on Karachi’s water supply system